Return to site

1 58 Deflection Track

broken image


Overall, deflection is literally defined as 'deviation from an allotted course'. It can mean that something is deviated by turning aside or by coming off course. For overhead cranes, this definition translates to the relative vertical or horizontal displacement of a member or part of an overhead crane. So how does that impact the design of the crane, and how is the vertical and horizontal deflection calculated? And, how do organizational specifications differ from crane to crane and from association to association? Let us explain.

Vertical Deflection Criteria

Seven-Eighths Mile Tracks: - HM S Hippodrome de Montreal 1:56.2 MOH S Mohawk Racetrack 1:54.4 WDB S Woodbine Racetrack 1:54.4 Five-Eighths Mile Tracks: - FRD F Fraser Downs 1:58.2 GEODF. Performance that stands up to deflection. For superior head-of-wall vertical deflection, and the added benefit of horizontal drift movement, ClarkDietrich introduces two solutions—MaxTrak® Slotted Deflection Track and MaxTrak® 2D Slotted Deflection & Drift Track. The MaxTrak System allows the top of the wall stud to float within the track legs.

Of a fundamental parameter, called the track modulus, which represents the effects of all the track components under the rail (1). Track Modulus (represented by u in this paper) is defined as the supporting force per unit length of rail per unit rail deflection (2). Track Stiffness (represented by k in this paper) is simply the ratio of applied. 1 hour partition with deflection track 5/8' fire-shield gypsum board 3 5/8' steel stud 24' o.c. 5/8' fire-shield gypsum board steel track - mechanically fasten 24' o.c. Glass fiber insulation (optional) flexible sealant (optional) firestop sealant mineral wool insulation concrete on fluted steel deck mechanically fasten deflection.

Vertical Deflection Criteria is the maximum (vertical) deflection ratio allowed for a lifting device. Vertical deflection differs from horizontal deflection, but both are taken into account for enclosed track bridge cranes. Vertical deflection impacts any part of the crane that stands vertically, including the mast, columns, wall, etc.
Most systems are manufactured to an approximate deflection, because manufacturers have no control over installation, foundation rigidity, or the standard variation in thickness tolerances for the piping, tubing, steel plate, and sheet metal. That means, some variation above or below deflections defined by manufacturers should be considered normal. That being said, when overhead cranes are installed according to the standard installation manual and maintained according to the manufacturers installation maintenance manual, you can be assured of the safety of lift products and their ability to handle chosen rated capacities and performance standards.

When measuring deflection for safety standards, the deflection is measured at 100 percent capacity, rather than 125 percent capacity. According to ANSI Standards (ANSI/ASME B30.2) for Overhead Travelling Cranes Operational and Running Tests: 'Standard deflection must be measured with a load of 100 percent of the rated capacity and must not exceed the allowable deflection specified by the applicable design standard.' For each type of crane the deflection value differs, depending on the crane's overall length, span, or reach.

For workstation (enclosed track) bridge cranes, the vertical deflection value is less than for heavier bridge cranes. Enclosed track workstation bridge cranes have a deflection limit of L/450. The letter 'L' literally stands for the length of the crane, or span. In other words, to determine the deflection of your workstation bridge crane, you must first know its span or length. This equation is always measured in inches. That's because if your deflection is higher than a value measured in inches, you're in big trouble. Deflection should be very minor. To measure your deflection, use the deflection limit defined for that type of crane and divide that number by the length (or span) of your specific system. If your bridge length is 34 feet, you will divide the deflection limit defined by your manufacturer (L/450 for workstation bridge cranes).
The deflection for a 34-foot bridge on a workstation bridge crane can be determined by first changing the unit of measurement from feet to inches. A 34-foot bridge is 408 inches long (feet x 12= inches). Divide 408 inches by the specified deflection limit for enclosed bridge cranes (L/450). That will give you a deflection of less than one inch (.9 inches).

Deflection is determined for other overhead crane systems using the same method. The criterion is the same, but the terminology and deflection limits differ slightly from system to system. For instance, when determining the deflection for a workstation (enclosed track) bridge crane, we would use a deflection limit of L/450, as specified above. However, when determining the deflection for a gantry crane, the deflection limit is L/600 for steel gantries, and L/450 for aluminum gantries. Steel will almost always have a slightly higher deflection limit due to its rigidity compared to that of aluminum. To determine the deflection of an all-steel gantry with a span (beam length) of 25 feet, you would follow the same equation we used to determine the deflection for workstation bridge cranes, only using the deflection limit for steel gantry cranes. In order to do so, we would first have to change the unit of measurement to inches. A span of 25 feet (multiplied by 12) is 300 inches. Next, we would determine the deflection by dividing the span of the gantry in inches by the deflection limit specified by the manufacturer. For Spanco, this number is, as specified above, L/600. A gantry crane spanning 300 inches has a deflection of a half an inch (.5 inches).

To determine the deflection for a jib crane, the equation remains the same, but the terminology can also differ from system to system, and the deflection limits differ once again. Some manufacturers will refer to the length or span of the jib as the 'reach'. That's why you might see a deflection limit for jib cranes referred to using the letter 'R' rather than the letter 'L'. It depends on your manufacturer. But, for the purpose of determining your deflection, keep in mind that 'R' simply stands for 'Reach' and 'L' stands for 'Length'. Whether it's referred to as the reach, the span, or the length is irrelevant in this case. The deflection equation still remains the same. When determining the deflection for jib cranes, the type of jib in question is also an important factor.

1 58 deflection track sizes

At Spanco, we have five different jib crane series, and each series has several installation types that impact the deflection limit. For instance, our 100 Series Freestanding Jib Crane has a deflection limit of L/150 (also known as R/150). That number is the same for our 200 Series Mast-Style Jib Cranes and our 300 Series Wall-Mounted Jib Cranes. However, our 400 Series Articulating Jib Cranes have a deflection limit of L/200 (or R/200), and our 500 Series Workstation Jib Cranes have a deflection limit of L/150 OR L/225, depending on the way the crane is mounted. For Freestanding Workstation Jib Cranes, there's a lower deflection limit. But for our 501 Series Wall-Cantilever Workstation Jib Cranes, we use a higher deflection limit of L/225 due to its wall-mount. For a 501 Series Wall-Cantilever Workstation Jib Crane, the deflection for a crane with a 12-foot span can be calculated similarly to the abovementioned systems. First, we would need to change our unit of measurement to inches. In this case, a 12-foot span (or reach) is equivalent to 144 inches. If we divide 144 inches by the deflection limit of 225, we get a deflection of a little more than a half an inch (.64 inches).

Horizontal Deflection Criteria

Horizontal Deflection Criteria is the maximum deflection ratio allowed for a bridge crane or runway. Horizontal deflection, unlike vertical deflection, impacts parts of the crane that run horizontally. This is taken into account for enclosed track systems, including workstation bridge cranes and workstation jib booms.
Most manufacturers design for a maximum lateral deflection for runways and cranes of L/400. The 'L' in this case refers to the span of the bridge crane from the runway support center. That number is divided by the deflection limit of 400. For example, to determine the deflection for a ceiling-mounted workstation bridge crane with bridge length of 40 feet, we must first translate the unit of measurement to inches. A 40-foot span is equivalent to 480 inches. If you divide 480 inches by the specified deflection limit of 400, the horizontal deflection for that particular crane is 1.2 inches.

Rigidity Requirements

It's crucial for manufacturers to conform to theoretical considerations and to subject their systems to a variety of checks like stress analyses and horizontal and vertical deflection analyses of bridges, beams, masts, columns, and other parts. These systems should prove to conform to theory and their static structural response must preserve the response of the original crane structure in order to pass these tests.
According to rigidity requirements laid out by OSHA and ANSI the following maximum values for the deflection of the crane girder must normally not be exceeded in order to avoid undesirable dynamic effects and to secure the function of the crane:

  • Vertical deflection is defined as the maximum permissible deflection ratio allowed for a lifting device. For bridge cranes this value is usually L/700. For a Workstation Bridge Crane, the value is less (L/450) because the enclosed track is lighter.
  • Horizontal deflection is a maximum deflection ratio allowed for a bridge crane or runway. For regular bridge cranes, this value is usually L/600. For a Workstation Bridge Crane, the value is less (L/400).

In the absence of more detailed calculations, it is acceptable to assume that the top flange resists the whole horizontal force. The rigidity requirement for horizontal deflection is essential to prevent oblique traveling of the crane. The vertical deflection is normally limited to a value not greater than 25 mm to prevent excessive vibrations caused by the crane operation and crane travel.

Testing Requirements

According to OSHA and ASME, crane load tests are typically specified at 125 percent of the crane's rated capacity. Neither standard, however, specifies an acceptable tolerance over or under the 125 percent figure. ASME B30.2 does in fact reference a figure in its interpretation of load testing, which suggests a tolerance of 0%/-4% on the weight of the test load. In effect, this suggested a test load weighing between 120 percent and 125 percent of the rated crane capacity (i.e.: 125% -125% x 0.04 = 120%).

Furthermore, any overhead crane that has been significantly modified, or that was installed after January 1999, must be load tested before being put into service. The deflection test defined by OSHA and ASME suggests that structural deflections must be measured with loads of 100 percent of the rated capacity and must not exceed the allowable deflections specified by the applicable design standard (deflection limits, as listed above). OSHA and ASME also specify that the load must travel over the full length of the bridge and trolley runways during these load tests, and only runway parts that have been successfully load tested may be placed into service.

If you have any questions about deflection or the deflection limit values outlined in this blog, please feel free to comment below. To ensure your deflection values are correctly calculated, it's important to reach out to your local overhead crane distributor or a qualified engineer for more information.

There are over 1,000 college track and field programs. Each division level has a different number of track scholarships they can give out each year. For men's programs a fully funded NCAA D1 or D2 track team will have 12.6 scholarships, NAIA programs have 12 scholarships. Women's track and field teams have 18 scholarships per team at the D1 level, 12.6 for NCAA D2 and 12 scholarships for NAIA programs. The vast majority of track scholarships are given as partial scholarships, but there is always the chance you can get a full-ride if you find the right program.

How to Get a Track and Field Scholarship

College Track scholarships are awarded to athletes by the coaching staff of each program. Each year coaches evaluate their team's needs and use their scholarships to award their top performing athletes as well as try and attract new athletes. For this reason, most scholarships are partial scholarships as coaches are dividing their track scholarships up to attract several top athletes.

In order to be a scholarship athlete you need to be able to come in and show potential early to be scoring points at the conference, regional and national level. For more information on track and field recruiting and how scholarships are awarded based on your event go here.

How Good do You Need to be to get a Track Scholarship?

Deflection Track Sizes

Unlike other college sports, coaches aren't watching hours of film and evaluating athletes at camps to know if they are going to be good enough for their team. Track and field is simple in the fact that either you can get the time or marks or you can't. That being said, each program has different needs and philosophies when it comes to awarding scholarship money. Unlike other college sports ,most track coaches will be very upfront about what time or mark you will need to make their team and to get a scholarship. The best thing you can do is contact the coaches staff and ask them what it takes to make their team and possibly earn a college track scholarship at their program.

Men's Track and Field

NCAA DINCAA DIINCAA DIIINAIA
55m IN6.32-6.706.35-7.206.78-7.206.52-7.20
60m IN6.61-7.106.65-7.406.92-7.406.81-7.50
55m hurdles7.4-7.97.65-8.18.0-8.28.0-8.2
60m HH IN7.75-8.007.89-8.508.29-8.508.21-8.50
300m IN33.94-35.8034.99-37.9036.78-39.0034.99-39.00
500m IN1.05.58-1.08.981.07.45-1.10.331.10.01-1.13.561.09.56-1.12.45
600m IN1.21.08-1.24.671.22.34-1.28.451.27.55-1.30.551.23.44-1.25.65
1000m IN2.28.55-2.32.442.31.33-2.37.442.38.43-2.42.442.32.32-2.38.66
3000m IN7.54.15-7.59.447.54.22-8.00.558.00.44-8.14.668.15.55-8.30.32
11om HH13.75-14.5014.13-15.3014.51-16.5014.62-15.55
300m IH35.92-38.5038.02-43.0039.67-44.0040.55-45.00
400m IH50.58-56,0052.76-60.0053.39-63.0054.87-60.00
100m10.13-10.9010.44-11.2010.65-11.4010.68-11.30
200m20.87–22.2021.90-23.0022.34-24.5022.02-23.0
400m45.68-49.9047.09-52.0048.61-54.0048.82-52.00
800m1.47.58-1.551.52.53-1.571.54.32-1.58.441.55.31-1.58
1,500m3.36.42-4.03.564.04.19-4.25.334.07.34-4.20.664.02.45-4.16.44
1,600m4.04.23-4.23.444.12.34-4.33.664.17.45-4.42.554.12.33-4.39.56
3,000m Steeplechase8.49.29-9.509.32.44-10.159.19.05-10.309.38.5-10.30
3,200m8.47.75-9.30.438.59.34-9.45.569.23.56-10.13.449.09.45-10.01.66
5000m XC14.20-16.0515.50-16.3017.00-17.3016.12-17.00
High Jump7'5″-6'6″6'10'-6'4″6'8″-6'0″6'6″-6'4″
Pole Vault18'5″-15'0″16'11'-14'0″16'2″-15'0″15'7″-14'0″
Long Jump24'4.25″-22'0″24'1″-20'0″23'9″-18'6″20'0″-18'0″
Triple Jump52'4.75″-44'0″49'10'-42'0″48'7″-40'0″47'11'-42'6″
Shot Put63'11.5″-55'6″56'5″-48'6″55'7″-46'5″54'3″-49'5″
Discus193'1″-167'0″173'3″-156'0″171.3″-140'0″161'0″-120'0″
Javelin225'8″-198'0″211'3″-155'0″208'2″-150'0″185'5″-135'6″
Hammer212'10'-170'4″203'2″-175'4″194'1″-165'3″188'6″-150'4″
Decathlon7666-6100 points6342-5600 points6239-4500 points6388-4700 points

Women's Track and Field

NCAA DINCAA DIINCAA DIIINAIA
55m IN6.95-7.357.25-7.757.90-8.257.40-8.00
60m IN7.31-7.857.30-8.507.80-8.507.68-8.50
60m HH IN8.16-8.808.36-10.08.95-10.208.93-10.0
300m IN39.20-41.0540.00-42.3242.03-45.0040.07-44.00
500m IN1.15.94-1.18.451.17.44-1.20.451.22.56-1.25.441.19.67-1.22.93
600m IN1.34.31-1.36.541.35.23-1.39.341.38.67-1.44.331.39.23-1.42.34
3000m IN9.18.54-9.23.459.19.56-9.29.449.28.60-10.0010.26.69-10.37.00
100m HH13.12-14.7014.18-15.6014.26-17.5014.56-17.50
300m IH41.80-45.7044.39-48.0047.56-49.5045.66-48.50
400m IH57.15-65.5060.99-67.0062.45-75.0064.03-75.00
100m11.23-12.2011.90-12.8012.12-13.2012.03-13.50
200m23.00-25.4023.90-26.5024.58-28.5024.57-28.00
400m52.06-58.5054.88-63.0056.72-67.0056.14-62.50
800m2.04.18-2.152.06.99-2.272.10.65-2.322.15.21-2.25
1,500m4.13.30-5.154.30.45-5.184.40.76-5.204.39.74-5.15
1,600m4.39.32-5.235.03.44-5.455.05.67-6.005.01.44-5.47
3,200m10.08.11-11.3210.29.45-12.0010.35.67-12.3010.26.69-12.00
5,000m XC16.53-18.5017.59-19.4521.12-32.0018.23-22.04
3,000m Steeplechase10.07.99-12.0011.23.87-12.5011.39-12.3011.49.25-12.25
High Jump6'00'-5'4″5'8″-5'2″5'5″-4'9″5'6″-5'0″
Long Jump20'6.25″-18'0″19'0″-16'3″19'0″-16'0″19.1″-16'0″
Shot Put55'1″-43'5″47'3″-39'6″44'8″-34'0″44'11'-36'0″
Discuss174'1″-147'9″153'0″-113'6″143'6″-110'4″121'3″-100'0″
Pole Vault14'0″-12'0″13'0″-11'6″12'5″-10'0″12'0″-10'0″
Triple Jump42'9″-38'6″40'4.5″-32'5″39'1″-31'5″37'10'-30'6″
Hammer206'9″-170'4″182'0″-146'4″170'6″-120'3″157'5″-110'6″
Javelin172'1″-141'0″149'0″-127'0″138'5″-112'3″117'10'-100'0″
Heptathlon5558-4000 points4915-3500 points4691-3000 points4223-3000 points

Fire Rated Deflection Track

NCAA D1 Track and Field

This is the top level of college track and field. The athletes that are competing here are among the best in the world. For many athletes just competing at this level never mind getting a scholarship can be a tremendous accomplishment. It is always good to have a couple D1 schools on your list but if your times or marks don't match up to the athletes currently on the team you might need to look at the other division levels.

NCAA D2 Track and Field

Many of the athletes at the NCA D2 level have the times or ability to make the team at the D1 level but choose D2 because they can get a better scholarship package and be more competitive. This doesn't mean the competition level is low, in fact the winning times and marks at D2 are often very close to the D1 times. The biggest difference is the depth of talent. If you are a fringe D1 athlete, you can compete at the D2 level and be much more competitive and probably get a bigger scholarship.

NCAA D3 Track and Field

Without the ability to offer athletic scholarships many people feel that D3 sports and track and field in particular are among the purist forms of competition. Athletes at this level could compete at the D2 level but have chosen D3 usually because the school is a better fit for them. If your times match up with D3 times, take the opportunity to get to know the some of the schools. You can search for NCAA D3 colleges here. You might find the perfect fit for continuing your track and field career while getting your degree.

Deflection Track Detail

NAIA Track and Field

For a long time people thought NAIA and D3 schools were the same levels of competition. Over the last few years NAIA track and field has started to show they are much more competitive and actually close to the D2 caliber of athletes. If you are looking for schools in the Mid-West or Southern parts of the US, look at the NAIA level.

1 58 Deflection Track Detail

IMPORTANT:NAIA Rule Changes. You must now register with theNAIA Clearinghouse.

Junior College Track and Field

1 58 Deflection Track Sizes

The junior college level has a very wide range of talent in track and field. Some athletes are at the Junior College level because they are academically ineligible to be at the D1 level. Other athletes didn't quite have the times or marks to move straight on to a four year school so they are at a junior college working to improve and move on after a couple years. Scholarships can be hard to find at this level because many programs aren't fully funded or if they are, they are restricted in how they can use their scholarships. You will need to check with each program and coach to see what opportunities are available.





broken image